Capital Projects

Print

ENGINEERING

Village Capital Projects

Aero Club Multi-Use Pathway
Project Status Update:  Contractor has completed all punch list items and continues to complete the final documentation to close out the project.  The project closeout should be completed in 2 weeks.

Big Blue Trace/Barberry
Status Update:  Survey and design work is currently underway.  Construction is anticipated to commence in June 2017.

Big Blue Trace/Wiltshire
Status Update:  Survey and design work is currently underway.  Construction is anticipated to commence in June 2017.

Blue Cypress
Project Status Update:  The contractor is continuing to complete the punch list items.  The project closeout should be completed in 30 days.

C-25 Canal Widening Project:
Project Status Update:  The contractor is completing the final documentation to close out the project.  The project closeout should be completed in 2 weeks. 

Forest Hill Boulevard/C-8 Canal Improvements
Project Status Update:  Survey and design work is currently underway.  Construction is anticipated to commence in July 2017.

Forest Hill Boulevard C-13 Canal Culvert Replacement Project:
Project Status Update:  Construction is substantially complete.  Additional asphalt cores were taken on February 16th. The contractor is also preparing the final closeout package for staff review.  The project closeout should be completed in 30 days.  

Pierson Road Alignment Project:
Project Status Update:  The project is substantially complete.  The project closeout should be completed in 30 days.  

Pierson Road/South Shore Boulevard Northbound Right Turn Lane Extension
Project Status Update:  100% design plans were received on February 9th and are currently under final review.  .  

Public Works Retention Area Project
Project Status Update:  The project is on hold until the site master plan is complete.  A project meeting will be held with the Architect next week.  

Stribling Road/Fairlane Farms Road Round-a-Bout Electrical and Lighting Improvements:
Project Status Update:  With the exception of three light poles which should be delivered to the project site by February 22nd, the remaining lights have been operational since February 15th.    

Stribling Road/Fairlane Farms Road Round-a-Bout Landscape:
Project Status Update:  This project is on hold until the lighting improvements are completed.  

Wellington Community Center:
Project Status Update:  The contractor continues to finalize the punch list items for the project.  Weekly punch lists walkthrough’s will be performed until Final Completion.

Hawthorne Neighborhood Park Project:
Project Status Update:  The Village Council approved the continuing contract proposal for the phase 2 construction at the January 24th meeting in the amount of $94,383.03.  Construction is anticipated to commence on April 10, 2017.

Dorchester Park Observation Platform:
Project Status Update:  The project is currently in the design and permitting phase.  Construction is anticipated to commence in June 2017.  

Assessment Projects


Saddle Trail Park (South) Neighborhood Improvement Project:
Project Status Update:  Village staff is waiting on the required final documentation and final pay application prior to closing out the project.  The project closeout should be completed in 30 days.  The purchase order for the horse crossing signage and lighting was process February 15th.  

Miscellaneous Projects

Birkdale Drive Guardrail:
Project Status Update:  The project is complete.  

W.W.T.P. Wetland Preserve Boardwalk Refurbishment Project:
Project Status:  The project is on hold as requested by the Utility Department.  

Permitted Projects

40th Street Improvements – C-4/C-24 Culvert Project:
Project Status Update:  Construction commenced on February 15th with the setting of the headwalls.  The 72” reinforced concrete pipe (RCP) will begin installation on February 16th and should be completed by February 17th.    


 

UTILITIES – Capital Projects

Project 201110 – Water Supply Improvements  
Raw Water Supply Evaluations: Kimley Horn Authorized January 25th
Completion Date March 2017

Project 701014 – Water Treatment Plant Renewal and Replacement 2017
Final Design: Kimley Horn Authorized January 25th
Completion Date May 2017

Project 702026 – Wastewater Treatment Plant Renewal and Replacement 2017

Final Design: Kimley Horn:  To Council March 28th

Project 201034 – Water Distribution and Transmission Improvements
Hydraulic Model Development: Mock Roos:  To Council March 28th

40th Street Water Main Replacement:

  • New watermain installed.  Final tie-ins to be complete next week.
  • Old watermain removed.


Project 702512 – Lift Station Upgrade

Wellhead Mechanical, Electrical and Control Upgrades:  9 Stations
  • Preliminary Design Report:   Mock Roos & Associates Authorized January 25th
    Completion Date:  May 2017 
  • Lift Station 92 Evaluation: Mock Roos & Associates Authorized December 16, 2016
    Completion Date:  February 2017
Project 201704 – Force Main Improvements
Hydraulic Development: Mock Roos & Associates:  To Council March 28th 

UTILITIES – Ongoing Non-Capital Projects/Efforts

Water Plant Sanitary Survey – PBC Health Department – August 2016
All work complete with the exception of replacing lime plant aerator.  Project is currently out to bid.  Bid to be received February 23rd.  

Water/Wastewater Plant Generator Emissions
Global Tech PO has been issued and they are currently developing the specifications.  Completion scheduled for February 2017

Water Plant Consumptive Use Permit and Permitted Capacity Review
JLA Geosciences PO has been approved and work is ongoing.  Preliminary report to be complete mid-February.  

Comprehensive Utility Systems Financial Performance Review
EFG Financial Services PO has been issued and the work is ongoing.  Preliminary report to be complete the end of February 2017.  

Update the 2006 Village Utility Construction Specification and Standard Details Manual
Revision has been inititated and is expected to be complete in April of 2017.  

Update the Utility GIS Mapping Layers
All distribution and collection data has been collected.  Have inititated quality control checks on water.  GIS data collection ongoing for grease traps and backflow preventers.  GIS data collection for reuse has not commenced.  

UTILITIES – Requests for Proposals
CCNA RFP to be issued this weekend for the following services:

  • General Hydrogeological Consultant
  • Utility Electrical, Instrumentation and Control Engineering ConsultantGeneral Wastewater Treatment Process Collection and Reclaimed Water Engineering Consulting Services